Over the last month all inspections for framing, electrical, plumbing, mechanical and wall insulation have been passed!!
Our staff with the help of our regular volunteers, partner families, and the PG Long volunteer day we have been able to complete hanging all of the drywall in unit 6 and are well into completing the drywall in unit 5.
Next step for these 2 units in building 3 will be tape and texture, paint and then interior millwork.
The Chambers Construction Apprenticeship Program apprentices have been slowly working on the exterior siding and trim as part of their training program and “In kind donation” of labor to HFHCL. We couldn’t do this work without the generous support of our many partnerships such as the one we have with Chambers Construction and their apprentices in the Apprenticeship Program!!
We are moving along at a good clip!