October 17, 2023
Update on Building 3
Over the last few weeks we have had all of the sub-contractors and IBEW electrical apprentices working on the utility rough ins such as plumbing, HVAC, and electrical. Rough in inspections for these utilities have been passed!!
Next stage for this building is to get the final frame inspection on Thursday.
Below, you can see the work completed on the community sidewalk; we’re starting to connect everything together 1 pour at a time.
We have also brought in about 100 cu yds of rock on R street over the last few months. Raising grade and working the site as we get the buildings up so we can prepare for the final finish landscaping and hardscaping.
Bioswale: The rain garden and all the new trees made it through the summer and are doing great now in the bio swale rain garden.
Fischer Village is shaping up and coming together!