March 8, 2023
While we’re waiting for materials to arrive to finish units 3 and 4 (building2) we have also been hard at work on the future foundations, under-slab utilities (plumbing, data, and electric) for buildings 1 and 3.
We passed our initial setback inspections on building 3 and are in the process of getting the foundation and plumbing inspections complete.




All of the footings are dug. Forms are good to go. The electric and data lines have been installed and inspected. We are waiting for the plumber to wrap up under-slab supply and drain lines this week with the help of our volunteers and we will install the vapor barrier.
Once the vapor barrier is in place, we do all the ironwork and then we will be good to pour after a few foundation and plumbing inspections.
Things are coming along!