Next week – Sheet rocking

Habitat Yogi Way - 8-16-14 - 17The Yogi crew has been working very hard!  They have been moving mountains of gravel and digging holes for fence posts.  The posts are placed and the crew is framing the front sidewalk and driveway.  The roofing is completed and the electrical installation is being finished now. Yesterday the crew from LEVI was on site and installed the wonderful denim insulation. Thank you LEVI!  Next week the team will start the work on the interior walls.